■ SERVICE – PROJECT
o2025 : Commissioning (Phase 1 : 2 x Lines)
• 2022 : ESB International / Design Contract $3.8 million (Phase 1)
• Project (2050): 109 km (4 x Lines)
o29 km: 2 x Lines (Phase 1)
o20 x Stations (Phase 1)
o43,000 Passengers per hour (per direction)
o Owner: Bahrain Ministry of Transportation and Telecommunications (MTT)
■ ROLLING STOCK – MAINTENANCE
oAutomatic driverless metro (GoA4)
o1 X Maintenance Workshop
oPPP (Public Private Partnership)
•Design & Specifications / Tenders (in progress)
■ Tender for Phase 1 : Design Build Finance, Operation & Maintenance
● Compagnies from Bahrain,India, China, French, Italy :
Almoayyed Contracting Group
GFH Financial Group
Larsen & Toubro
Delhi Metro Rail Corporation Ltd
China Railway Group Limited
China Railway Construction Co., Ltd.
China Harbour Engineering Co. Ltd
Five Capital
Alstom
Hitachi Rail
Webuild
■ COST – INVESTMENT
o~ $2 Billion for 29 km (Phase 1)
o~ $68.9 Million per km
=> Sources / Credits :
▪︎ Bahrain Ministry of Transportation and Telecommunications (MTT)
▪︎ NewTrain : Post (Picture & Video Editing / Text)
=> Thanks for sharing by using “linkedin Post button “
🍀🚆🍀
■ NewTrain
www.newtrain.com
***
“Free Railway Contents & Informations “
=> Subscribe linkedin page : 👉 NewTrain
=> Follow (new post) : 👉 hashtag#newtrain
=> Check website : 👉 www.newtrain.com
■ NewTrain
#metro #Bahrain #railway #mtt #rail #railway #PublicTransport #transportation #trains #newtrain